Sunday, September 20, 2015

The logistics of water and sewer

Very confusing working with the Municipio workers via the bungalow owner on the corner who also works for the Municipio and two lot owners who are not here via email. We heard at the last minute that if we buy the pipe they will run sewer up the road in front of the lots. This is just as I'm ready to call in a backhoe to dig for a water line. So we get the 8" sewer pipe and the water project goes on hold because you can't have two ditches on the road. 

Saturday was supposed to be the last day the workers could be there so a few people were getting frantic. That was simply bad info from the bungalow owner because when I showed up on Saturday the news was they will work until the work is finished. Now that makes sense!

Friday we were there to mark the water line and mark off the lot for the backhoe who might be able to trench for the wall foundation. We were just about finished when the workers showed up and started digging a registro in the middle of the intersection. I told the bungalow owner we could pull our cars out now so we could leave when we wanted and he just shrugged he shoulders and we were trapped for 2.5 hours. I finally asked the backhoe driver to smooth a path for us to one side and he did. Now we just wait until the sewer is finished and work on the water later

Incoming 12" sewer line

Registro on the corner

Us waiting in our trapped position

Sunday, August 23, 2015

Trying to get city water


The picture is a little more than half of the 60 meters we need to run a water pipe. Friends have two lots to the left under that large tree and I'm trying to get water there before construction starts in November. It seems that if you don't have a 2" mainline in front of your property you have to install that as well. A water contract with San Patricio is 1800 pesos but only includes 6 meters of 1/2" pipe. The 60 meter run is going to cost about 2500 pesos for material, 1200 for a backhoe and whatever a plumber charges to lay the 2" pipe.

The biggest problem is communication with the lot owners. The Canadians are very slow on email responses and Ron left San Miguel for Seattle about a week ago and I haven't heard from him. I assume Ron drove but maybe they flew and will rent a car. The two hangups so far are money and full sized (legal) copies of all the lot papers. So I wait to see what they can do for copies if they have them all and for some money deposited to my account.
The construction of the house finished in April 2011 and I'm pretty much settled in. As of March 2014 I'm in preparation for rain mode for this coming summer. That includes sealing and painting things and dealing with drainage issues from last year.