Wednesday, April 17, 2013

What do you do with ....

What do you do with a section of grass that seems unable to recover mostly due to a dog that excavates to cool off. Basically pave it!! The problem with bricking it all is water drainage from the shed roof above so I decided on that gravel strip. If that area wasn't dirt it was mud and both getting tracked everywhere. Clean is good.

What do you do with a door that you don't use .... brick it in!! For a long time I've talked about filling in the door that was originally designed as a second entrance to the other lot. The lots won't ever be separated so it's only a window for my dog to bark at kids passing in the street. It wasn't very attractive and the metal requires upkeep. I ordered way too many bricks for the patio so Hugo said why not use them for the door. And he needed the work.

New patio with shed roof above

No dirt showing now

Hugo filling in the door

Tuesday, April 26, 2011

The new lawn

Against the advice of a few people that meant well I went with grass. This will mean more upkeep and water but but a gravel yard just does not get it for me. This is Bermuda grass and I got it through the vivero (nursery guy) near the Jaluco intersection on the way to Barra. Also got two lime trees from him.

I ordered 50 meters and sent some home with one of my workers. Price for the pasto (lawn) was 35 pesos a square meter. I think I overworked placing and cutting and didn't drink enough water so stayed in bed 'till noon today.

Still have almost half the property unplanned except for a few trees and plants. Think it will just sit while I finish the house. Hugo started painting grout joints with sealer today and I'll join him tomorrow.



Sunday, November 07, 2010

Is all that gonna fit on my roof

Two loads of sand, one and a half loads of gravel and 100 bags of cement. Of all that we had about a half load of sand left, a quarter load of gravel and used exactly 100 bags of cement. There is also about 120 pieces of six meter rebar under the cement on a 120 square meter roof.

No cement pumpers used here - it was the bucket by bucket brigade up the street side of the house. Street was closed to all but bicycles for almost 4 hours. The roof foto only shows the beginning of the pour but it is all up there. My job now is to water the roof at sunrise and sunset so it dries slowly.

Sand and gravel in the street

100 bags of cement

About a quarter of the way thru the pour

Cement crew in the street

The construction of the house finished in April 2011 and I'm pretty much settled in. As of March 2014 I'm in preparation for rain mode for this coming summer. That includes sealing and painting things and dealing with drainage issues from last year.